Activities
1) Duration: 3 months
Working out the feasibility study for the sewage system of surrounding villages – main goal is to find which is the more cost-efficient and ecologically sound solution – to connect the sewage systems of those villages to the sewage treatment plant in Zagreb or the one in Velika Gorica.
2) Duration: 6 months
Working out the environmental impact study for the innovation and improvement of the municipal waste-water treatment plant in Velika Gorica.
3) Duration: 2 months
Working out the documentation needed for receiving the site permit for the reconstruction of the municipal waste-water treatment plant in Velika Gorica.